Construction Drying Hemel Hempstead | Ideal Response

Available 24/7 | 0800 088 4170

Accelerating construction drying across a major Hemel Hempstead development

Two 32-apartment buildings, an underground car park and winter-saturated concrete demanded a drying system designed at development scale.

Ideal Response commercial fire damage restoration project
Location
Hemel Hempstead
Duration
25 Working Days
Service
Specialist Drying
Sector
Construction

A series of winter storms hit a major residential construction project in Hemel Hempstead before the buildings were fully watertight. Rainwater and high humidity left two apartment blocks and an underground car park heavily saturated, with moisture held through concrete screeds, walls and soffits.

Another restoration contractor had already spent five weeks on the problem with limited progress and estimated that a further six weeks would be needed. With the construction programme slipping and potential Liquidated and Ascertained Damages increasing the commercial pressure, Bugler Developments needed a faster, measurable route back to dry construction conditions.

From winter exposure to a development-wide moisture problem

The two buildings had remained exposed during the latter part of 2020. By the time the drying requirement was assessed, relative humidity was above 80% across parts of the site, with project readings reported above 85% in the wettest areas. Moisture checks through the floors found conditions ranging from total saturation to progressively lower moisture loading towards ground level.

This was not a collection of isolated wet rooms. A Block extended across four floors and B Block across five, while the wider published project scope also included the underground car park. The drying strategy therefore had to influence large volumes of concrete construction while responding to different moisture conditions across the development.

The operational drying target was 60% RH. Raising the temperature of the concrete soffits and screeds was central to the plan: reducing condensation while encouraging retained moisture to evaporate from the building fabric.

A 750kW oil-fired packaged boiler provided the primary heat source, supported by a bespoke air-handling system and specialist ducting to distribute heat through the active block. More than 248 monitoring points tracked relative humidity, temperature and moisture across the development. Barcode-enabled scanners supported ongoing data capture, with moisture mapping paired with Matterport 3D visualisation to give the team a spatial view of drying progress. Boiler output could be adjusted remotely as external conditions changed, and equipment was repositioned as individual areas dried so capacity remained focused where it was still needed.

A drying system built around the development

The development was dried in controlled stages, using moisture surveys to define the problem, a 750kW industrial oil-fired packaged boiler as the central heat source and a block-by-block programme that concentrated heat and airflow where they were needed.

  • Mobilised rapidly, with the existing page recording survey and proposal within 24 hours of the initial enquiry.
  • Surveyed the development and took moisture readings through floors, concrete screeds and walls.

The scale of the loss called for a different approach from conventional portable drying. Ideal Response worked with sister company Ideal Heat Solutions to deploy a 750kW industrial oil-fired packaged boiler and standalone fuel tank, craned into position to provide the heat capacity required.

A bespoke air-handling arrangement distributed that heat floor by floor. Specialist ducting directed heated air into targeted areas, while insulating sheets were used around roof and wall areas during snow and frost to reduce unnecessary heat loss.

The site's gantries provided the preferred access route to the floors. Rather than trying to dry both blocks simultaneously, capacity was concentrated on one block at a time, working top-down while treating all floors within the active building together.


The equipment created the drying conditions; the monitoring system showed how the buildings were responding. More than 248 data-logging points were installed throughout the development to track relative humidity, temperature and moisture.

Barcode-enabled scanning allowed readings to be gathered consistently as the programme progressed. Matterport 3D visualisation was used alongside moisture mapping, giving the project team a clearer way to relate readings to their physical location within the buildings.

That information informed practical decisions on site. Heat output could be adjusted as outside temperatures changed, and equipment could be moved as sections reached the required condition rather than continuing to apply the same drying intensity everywhere.

248+ monitoring points turned drying into measurable progress

The first building reached the project's stated PAS 64 dryness goal in 14 days. The second followed within a further 11 days, bringing the two-block drying sequence to 25 days.

That was six weeks faster than the previous restoration contractor's projected remaining programme. For the developer, the significance went beyond moisture readings: recovering that time reduced exposure to construction delay and saved tens of thousands of pounds in potential LADs, while allowing critical follow-on works to move forward.

The result demonstrates what large-scale construction drying can achieve when heat generation, air distribution, moisture mapping and site phasing are designed as one system rather than treated as separate pieces of equipment.

Project insight

On a wet construction site, the biggest boiler is not automatically the best drying strategy. The stronger solution is to understand where the moisture sits, create a controlled route for heat through the structure, measure the response and keep concentrating capacity where it produces the greatest effect. At Hemel Hempstead, that meant combining 750kW of heat with bespoke air distribution, more than 248 monitoring points and a phased block-by-block programme.

From an estimated six more weeks to dry buildings in 25 days

Why construction drying should be managed with data, not dates

Yacine Melaab
Water Damage Specialist
“On a large development, a calendar alone cannot tell you when a building is ready for the next trade. Different plots and materials can dry at very different rates, especially after prolonged winter exposure. Repeated moisture readings create a measurable picture of progress so drying equipment can be concentrated where it is still needed and released where targets have been reached.”

Related information

Specialist DryingWater Damage

Need urgent help?

Call our team 24/7 on 0800 088 4170.

Send an Enquiry
Ideal Response technician setting up commercial drying equipment
Three Ideal Response technicians checking moisture levels of walls at a construction site.

Ideal Response technicians on site in Hemel Hempstead to dry the property prior to work commencing.